Replace your PM3255 monitoring with DEM-6MC
Plan your Schneider PM3255 replacement around the cabinet and signals already installed. Blue Jay DEM-6MC offers DIN rail power and energy monitoring with selectable CT inputs, published 0.5S active-energy accuracy and Modbus RTU. Its wider housing, dry-contact inputs and relay outputs need attention when replacing a PM3255 with voltage-operated inputs and static outputs. The comparisons below help you check mounting space, auxiliary power, signal conversion and the records your monitoring system must retain. Send a cabinet photo, the existing I/O diagram and sample logs to request a replacement configuration covering both the meter and the necessary installation changes.
Compare the Specifications Schneider PM3255
| Selection point | Schneider PM3255 | DEM-6MC | What this means for replacement |
| Nominal CT input | 1 A / 5 A | 1 A / 5 A options | Order the installed CT secondary; verify measurement and overload limits. |
| Active-energy class | IEC 62053-22 Class 0.5S | Class 0.5S in accuracy table | Request the accuracy evidence for the selected current-input version. |
| Dimensions W x H x D | 90 x 95 x 70 mm | Drawing: 108 x 110 x 66 mm | Allow 18 mm more width by the drawing, plus wiring clearance. |
| Voltage measurement | 50-330 V L-N; 80-570 V L-L, product measured ranges | 100 / 220 / 380 V options; verify connection and range | Specify the actual phase and line voltage for input selection. |
| Control power | 100-277 V AC / 173-480 V AC / 100-300 V DC listed | 85-265 V AC/DC table; p8 also states 90-240 V AC/DC | Confirm the supplied power range; redesign higher-voltage supplies. |
| Digital inputs | 2 DI, 11-40 V DC | 4 DI, dry contact | Use an agreed isolation or contact conversion design where needed. |
| Digital outputs | 2 static DO | 2 relay DO; 5 A at 250 V AC / 30 V DC listed | Check load, switching rate and pulse duties before reconnecting. |
| Serial speed | 9.6-38.4 kbaud | 1.2-19.2 kbaud standard | Use a common supported speed or agree a separate interface. |
| Logging | 512 KB; energy and power logs; 15 alarms | 60 SOE entries; three-month maximum-demand records | Define required intervals, retention and export; use external logging if necessary. |
PM3255 replacement configuration
Check and configure the replacement
1 Allow for the cabinet size
The PM3255 is listed at 90 mm wide. The DEM drawing shows 108 mm width, 110 mm height and 66 mm depth. Confirm the supplied drawing because the manual specification page reverses width and height.
2 Match CTs and power
Order the installed 1 A or 5 A input and confirm the network type and voltage. The DEM auxiliary-supply descriptions differ between manual sections; obtain the full range for the quoted hardware. A 400 V line-to-line supply needs a suitable power arrangement.
3 Convert the actual I/O circuits
Identify the voltage on each original DI and the load and switching rate on each static DO. The DEM uses dry-contact inputs and relay outputs. Agree any conversion equipment before transferring a tariff, alarm or counter signal.
4 Rebuild monitoring and history
Use a common serial speed and a new register map. Define the logs that must survive the change: the DEM SOE record is not a substitute for every interval energy or power log. Test acquisition and the agreed historical reports.
Applications for this replacement
Suitable for industrial feeder metering, building submetering for internal cost allocation and OEM DIN rail cabinets that can accommodate the new width and interface design. Projects with fixed logging, static pulse or approval requirements need those requirements confirmed separately.